Discover the hassle-free process of obtaining a TNEB new connection. Follow the step-by-step guide for online application.

We recommend the app

Redeem your earned rewards instantly!

What is TNEB (TANGEDCO) and how does its new connection process work?

What is TNEB (TANGEDCO) and how does its new connection process work?

TNEB, TANGEDCO and TNPDCL are the same single utility that supplies electricity across Tamil Nadu. The Tamil Nadu Electricity Board (TNEB) became the Tamil Nadu Generation and Distribution Corporation (TANGEDCO), and its distribution business is now the Tamil Nadu Power Distribution Corporation Limited (TNPDCL), though the portals still carry TANGEDCO branding.

Unlike states such as Delhi or Maharashtra that have several distributors, Tamil Nadu has one distributor statewide, so every TNEB new connection goes through the same tangedco new connection online process. This guide covers the documents, steps, cost and timeline for a new connection.

What documents do you need for a TNEB new connection?

For a TNEB new connection you need two core documents: an identity proof and an ownership proof. The table below lists what is accepted for a TNEB new service connection.

RequirementAccepted documentsNotes
Identity proofAadhaar, voter ID, passport, PAN or driving licenceAny one
Ownership proofSale deed, patta, property-tax receipt or court orderAny one
Tenant or non-ownerForm 5 (owner's consent letter) or Form 6 (indemnity bond) with occupancy proofForm 6 is a statutory right under Section 43 of the Electricity Act, 2003
Building completion certificateLocal authority certificateNeeded for larger or newer buildings; small residences are generally exempt

If you are a tenant and the owner will not sign Form 5, you can still get a TNEB new service connection by filing Form 6.

How to apply for a TNEB new connection online

You apply for a TNEB new connection online on the TANGEDCO new service connection portal at app1.tangedco.org/nsconline.

  1. Visit the TANGEDCO portal and open the new service connection section to start your TNEB new connection online apply.
  2. Create an account or log in. Note: on the payment portal (tnebnet.org/awp), your Application Reference Number is the username and your registered mobile number is the password, which is an unusual convention that confuses many applicants.
  3. Select your district, circle and area so your application reaches the correct office.
  4. Choose the category of supply: domestic, commercial or agricultural.
  5. Enter your load details, including the connected load in kilowatts, and select single-phase or three-phase supply.
  6. Upload your identity proof, ownership proof and any other required certificates. The section office also accepts paper applications, and authorised e-Sevai centres can file on your behalf.
  7. Submit the application and note the Application Reference Number (ARN) on the acknowledgement slip.
  8. Pay the demand raised against your ARN online once it is generated.

You then receive updates by SMS, and you can pay your future TNEB bills on Bajaj Finance.

How to check your TNEB new service connection status

You can check your TNEB new service connection status on the TANGEDCO portal using your application number.

  1. Go to the TANGEDCO Bill Status page.
  2. Enter your service connection or application number provided during the application.
  3. Enter your registered mobile number.
  4. View the status to see the sample SMS, bill receipt or white meter card showing your progress.

This tells you where your tangedco new connection online request has reached.

What does a new TNEB connection cost for a residential property?

A new TNEB connection for a home has three cost components: a registration or application fee, service connection charges, and a refundable security deposit.

Charge typeWhat it coversWhen payable
Registration or application feeFiling the online applicationAt submission on the portal
Development and service connection chargesThe TNERC per-kW schedule, higher if a line extension is neededAfter the section office inspection, payable online against your ARN
Security deposit (refundable)Sized to about two months of expected consumption, as Tamil Nadu bills bi-monthlyAfter the inspection demand; refundable with interest and trued-up each year

The exact amounts are set by the TNERC schedule and shown in the demand raised against your ARN. After your connection is live, pay your bills through TNEB electricity bill payment or the wider electricity bill payment page on Bajaj Finance.

How long does TNEB take to install a new meter after application?

TNEB installs a new meter within 7 days in Chennai metro after a complete, paid application. The table below shows the legal timelines by area.

Area typeLegal timelineAuthority
Metropolitan (Chennai)7 daysElectricity (Rights of Consumers) Rules, 2020
Other municipal areas15 daysElectricity (Rights of Consumers) Rules, 2020
Rural areas30 daysElectricity (Rights of Consumers) Rules, 2020

These timelines apply after a complete, paid application, and TNERC's Standards of Performance provide compensation where TANGEDCO defaults. Longer timelines apply only where genuine line-extension work is needed, so track your TANGEDCO new connection online request and escalate if it stalls.

Conclusion

Obtaining a new TNEB connection has become more efficient, thanks to online processes and streamlined procedures.

Whether you are setting up a home, office, or agricultural unit, follow the steps above to ensure a hassle-free experience. With TANGEDCO’s commitment to prompt service, you will have electricity flowing in no time.

Disclaimer

While care is taken to update the information, products, and services included in or available on our website and related platforms/ websites, there may be inadvertent inaccuracies or typographical errors or delays in updating the information. The material contained in this site, and on associated web pages, is for reference and general information purpose and the details mentioned in the respective product/ service document shall prevail in case of any inconsistency. Subscribers and users should seek professional advice before acting on the basis of the information contained herein. Please take an informed decision with respect to any product or service after going through the relevant product/ service document and applicable terms and conditions. In case any inconsistencies are observed, please click on reach us.

*Terms and conditions apply

Frequently asked questions

How do I apply for a TNEB new connection online?

Visit the official TANGEDCO portal and select "Apply for New Service Connection". Fill out the online form with applicant and property details, upload ownership proof (sale deed or property tax receipt) and ID proof, pay the registration fee online, and track your application using the generated reference number.

What is the difference between LT and HT electricity connections under TNEB?

LT (Low Tension) supplies 230V (single-phase) or 415V (three-phase) power for loads up to 112 kW, serving homes, shops, and small businesses. HT (High Tension) delivers 11 kV, 22 kV, or 33 kV for demands exceeding 112 kW, powering large industries, commercial complexes, and IT parks via dedicated transformers.

How many days does a new TNEB connection take after application?

Under TNERC regulations, a connection takes 3 to 7 days if existing distribution lines are available. If line extension or erecting new poles is required, it takes up to 30 days. For installations requiring a new distribution transformer or substation work, it can take 60 to 90 days.